Construction Project Management

Höfundur S. Keoki Sears, Glenn A. Sears, Richard H. Clough, Jerald L. Rounds, Robert O. Segner

Útgefandi Wiley Professional Development (P&T)

Snið Page Fidelity

Print ISBN 9781118745052

Útgáfa 6

Útgáfuár 2015

13.990 kr.

Description

Efnisyfirlit

  • Construction Project Management
  • Contents
  • Preface
  • 1 Construction Practices
  • 1.1 Introduction
  • 1.2 The Construction Industry
  • 1.3 The Construction Project
  • 1.4 Project Stages
  • 1.5 Owner
  • 1.6 Architect‐Engineer
  • 1.7 Prime Contractor
  • 1.8 Competitive Bidding
  • 1.9 Negotiated Contracts
  • 1.10 Combined Bidding and Negotiation
  • 1.11 Subcontracting
  • 1.12 Design‐Bid‐Construct
  • 1.13 Fast Tracking
  • 1.14 Construction Contract Services
  • 1.15 Construction Services
  • 1.16 Design‐Construct
  • 1.17 Construction Management
  • 1.18 Fixed‐Sum Contract
  • 1.19 Cost‐Plus‐Fee Contracts
  • 1.20 Work‐by‐Force Account
  • 1.21 Turnkey and BOT Contracts
  • 1.22 Integrated Project Delivery
  • 1.23 Speculative Construction
  • 1.24 Management during the Design Phase
  • 1.25 Management of Field Construction
  • 1.26 Project Manager
  • 1.27 Project Manager Qualifications
  • Key Points and Questions
  • 2 Systematic Project Management
  • 2.1 Introduction
  • 2.2 Need for Project Management
  • 2.3 Project Management Characteristics
  • 2.4 Discussion Viewpoint
  • 2.5 Management Procedures
  • 2.6 Time and Cost Management
  • 2.7 Planning and Scheduling
  • 2.8 CPM Procedure
  • 2.9 Time Monitoring and Control
  • 2.10 Project Cost System
  • 2.11 Estimating the Project
  • 2.12 Project Cost Accounting
  • 2.13 Resource Management
  • 2.14 Project Financial Control
  • 2.15 Automating Project Management Tasks
  • 2.16 Manual Methods
  • 2.17 Discussion Format
  • 2.18 Example Projects
  • Key Points and Questions
  • 3 Project Estimating
  • 3.1 Introduction
  • 3.2 Project Cost System
  • 3.3 Preliminary Cost Estimates
  • 3.4 Final Cost Estimate
  • 3.5 Example Projects
  • 3.6 Quantity Survey
  • 3.7 Management Input
  • 3.8 Field Supervision
  • 3.9 Construction Methods
  • 3.10 General Time Schedule
  • 3.11 Construction Equipment
  • 3.12 Summary Sheets
  • 3.13 Material Costs
  • 3.14 Labor Costs
  • 3.15 Indirect Labor Costs
  • 3.16 Labor Unit Costs
  • 3.17 The Cost of Heavy Equipment
  • 3.18 Bids from Subcontractor
  • 3.19 Project Overhead
  • 3.20 Home Office Overhead
  • 3.21 Markup
  • 3.22 Contract Bonds
  • 3.23 Recap Sheet
  • 3.24 Cost Models
  • 3.25 Project Budget
  • 3.26 Progress Estimate
  • 3.27 Estimating for Changes
  • Key Points and Questions
  • 4 Project Planning
  • 4.1 Introduction
  • 4.2 CPM Procedure
  • 4.3 Planning Phase
  • 4.4 Job Activities
  • 4.5 Job Logic
  • 4.6 Restraints
  • 4.7 Beginning‐to‐End Planning
  • 4.8 Top‐Down Planning and the Work Breakdown Structure
  • 4.9 Precedence Notation
  • 4.10 Precedence Diagram
  • 4.11 Network Format
  • 4.12 Lag Relationships
  • 4.13 Precedence Diagram for the Example Projects
  • 4.14 Value of Precedence Network
  • 4.15 Repetitive Operations
  • 4.16 Network Interfaces
  • 4.17 Master Network
  • 4.18 Subnetworks
  • 4.19 Computer Applications for Planning
  • Key Points and Questions
  • 5 Project Scheduling Concepts
  • 5.1 Introduction
  • 5.2 Scheduling Procedure
  • 5.3 Activity Times
  • 5.4 Rules for Estimating Activity Durations
  • 5.5 Estimating Activity Durations
  • 5.6 Time Contingency
  • 5.7 Project Weather Delays
  • 5.8 Network Time Computations
  • 5.9 Early Activity Times
  • 5.10 Project Duration
  • 5.11 Late Activity Times
  • 5.12 Total Float
  • 5.13 Critical Path
  • 5.14 Free Float
  • 5.15 Activity Time Information
  • 5.16 Float Paths
  • 5.17 Early‐Start Schedule
  • 5.18 Tabular Time Schedules
  • 5.19 Activities and Calendar Dates
  • 5.20 Calendars for Weather
  • 5.21 Lags between Activities
  • 5.22 Pipeline Scheduling Computations
  • 5.23 Pipeline Summary Diagram
  • 5.24 Interface Computations
  • 5.25 Hammock Activity
  • 5.26 Milestones
  • 5.27 Time‐Scaled Networks
  • 5.28 Nature and Significance of Floats
  • 5.29 Bar Charts
  • 5.30 Computer Applications for Scheduling
  • Key Points and Questions
  • 6 Production Planning
  • 6.1 Introduction
  • 6.2 Planning Team
  • 6.3 Reengineering the Project
  • 6.4 Planning for Production
  • 6.5 Support Planning
  • 6.6 Technical Problems
  • 6.7 Personnel Planning
  • 6.8 Safety Planning
  • 6.9 Planning for Quality
  • 6.10 Material Ordering and Expediting
  • 6.11 Material Handling, Storage, and Protection
  • 6.12 Equipment Planning
  • 6.13 The New Production Model
  • Key Points and Questions
  • 7 Managing Time
  • 7.1 Introduction
  • 7.2 Time Schedule Adjustments
  • 7.3 Need for Time Reduction
  • 7.4 General Time‐Reduction Procedure
  • 7.5 Shortening the Longest Time Path
  • 7.6 Project Direct Costs
  • 7.7 Variation of Activity Direct Cost with Time
  • 7.8 Project Indirect Costs
  • 7.9 Practical Aspects of Time Reduction
  • 7.10 Reduction of the Highway Bridge Duration
  • 7.11 Time Reduction of Highway Bridge by Expediting
  • 7.12 Least‐Cost Expediting of the Highway Bridge
  • 7.13 Limitations on Time‐Reduction Steps
  • 7.14 Variation of Total Project Cost with Time
  • 7.15 Expedited Highway Bridge Schedule
  • 7.16 Milestone and Interface Events
  • 7.17 Project Extension
  • 7.18 Time Management System
  • 7.19 Aspects of Time Management
  • 7.20 Key‐Date Schedules
  • 7.21 Adjustment of Move‐in Date
  • Key Points and Questions
  • 8 Resource Management
  • 8.1 Introduction
  • 8.2 Objective of Resource Management
  • 8.3 Project Resource Management
  • 8.4 Aspects of Resource Management
  • 8.5 Tabulation of Labor Requirements
  • 8.6 Project Labor Summary
  • 8.7 Variation in Labor Demand
  • 8.8 Manpower Leveling
  • 8.9 Heuristic Manpower Leveling
  • 8.10 Numerical Example
  • 8.11 Labor Leveling in Practice
  • 8.12 Restricted Labor Supply
  • 8.13 Complex Labor Scheduling
  • 8.14 Equipment Management and Scheduling
  • 8.15 The Construction Supply Chain
  • 8.16 Material Scheduling
  • 8.17 Resource Expediting
  • Key Points and Questions
  • 9 Project Scheduling Applications
  • 9.1 Introduction
  • 9.2 Role of the Schedule
  • 9.3 Operational Schedules
  • 9.4 Organizing Schedule Data
  • 9.5 Schedule Presentation Formats
  • 9.6 Schedules for Repetitive Operations
  • 9.7 Impacted Baseline Schedule
  • 9.8 But‐for or Collapsed As‐Built Schedule
  • 9.9 Legal Schedules
  • 9.10 Handling Weather Effects and Other Unknowns
  • 9.11 Presenting the Schedule
  • Key Points and Questions
  • 10 Project Coordination
  • 10.1 Introduction
  • 10.2 Schedule Information on the Job
  • 10.3 Detailed Schedules
  • 10.4 Subcontractor Scheduling
  • 10.5 Activity Planning
  • 10.6 The Last Planner Process©
  • 10.7 Production Checklists
  • 10.8 Look‐Ahead Schedules
  • 10.9 Planning the Paperwork
  • 10.10 Putting the Plans on Paper
  • 10.11 Progress Measurement
  • 10.12 Progress Reporting
  • 10.13 Bar Charts
  • 10.14 Highway Bridge as of July 14
  • 10.15 Weekly Progress Reports
  • 10.16 Field Progress Narrative
  • 10.17 July 21 Status of Highway Bridge
  • 10.18 Progress Analysis
  • 10.19 Schedule Analysis to Determine Project Delays
  • 10.20 Corrective Action
  • 10.21 Network Updating
  • 10.22 Updating Calculations Manually
  • 10.23 Scheduling Software
  • 10.24 Project Progress Curves
  • Key Points and Questions
  • 11 Project Cost System
  • 11.1 Introduction
  • 11.2 The Construction Cost Cycle
  • 11.3 Objectives of a Cost System
  • 11.4 Project Cost Control
  • 11.5 Data for Estimating
  • 11.6 Project Cost Code
  • 11.7 Usage of Project Cost Code
  • 11.8 Project Cost Accounting
  • 11.9 Labor and Equipment Costs
  • 11.10 Cost Accounting Reports
  • 11.11 Labor Time Reporting
  • 11.12 Time Card Preparation
  • 11.13 Measurement of Work Quantities
  • 11.14 Work Quantities from Network Activities
  • 11.15 Cost Records and Reports
  • 11.16 Weekly Labor Reports
  • 11.17 Weekly Labor Cost Report
  • 11.18 Equipment Cost Accounting
  • 11.19 Monthly Cost Forecast
  • 11.20 Time‐Cost Envelope
  • 11.21 Earned Value Management System
  • 11.22 Forecasting Final Project Results Using the EVMS
  • 11.23 Special Cost Accounting Problems
  • 11.24 Production Cost Reduction
  • 11.25 Information for Estimating
  • 11.26 Postproject Evaluation
  • 11.27 Software Applications
  • 11.28 Accuracy of Estimating
  • Key Points and Questions
  • 12 Project Financial Management
  • 12.1 Introduction
  • 12.2 Financial Control
  • 12.3 Progress Payments
  • 12.4 Pay Requests for Unit‐Price Contracts
  • 12.5 Project Cost Breakdown
  • 12.6 Pay Requests for Lump‐Sum Contracts
  • 12.7 Use of Time‐Control Activities for Pay Requests
  • 12.8 Pay Requests for Cost‐Plus Contracts
  • 12.9 Payments to Subcontractors
  • 12.10 Schedule of Payments by Owner—Unit‐Price Contract
  • 12.11 Schedule of Payments by Owner—Lump‐Sum Contract
  • 12.12 Final Payment
  • 12.13 Cash Flow
  • 12.14 Cash Disbursement Forecasts
  • 12.15 Cash Income Forecasts
  • 12.16 Disbursement Controls
  • 12.17 Project Changes
  • 12.18 Contract Change Orders
  • 12.19 Claims
  • 12.20 Daily Job Log
  • Key Points and Questions
  • Index
  • EULA
Show More

Additional information

Veldu vöru

Rafbók til eignar

Reviews

There are no reviews yet.

Be the first to review “Construction Project Management”

Netfang þitt verður ekki birt. Nauðsynlegir reitir eru merktir *

Aðrar vörur

0
    0
    Karfan þín
    Karfan þín er tómAftur í búð